Unguided Auger Boring at Braden Trunk Main PSC Mains Renew, Irvine, Scotland. M238

Client
Scottish Water Plc

Project
Irvine Bypass Trunk Main Scheme

Description

The new “Irvine Bypass Trunk Main Scheme” is a strategically important trunk main project. The existing Bradan trunk main runs from the Highlees South SR to Greenhead DSR and feeds approximately 39,785 properties.

A section of the existing Bradan Trunk Main which is laid through Irvine in 33”/ 36” Pre-stressed Concrete (PSC) is to be replaced with SDR 17 PE main. The new main will be laid from Drybridge, located to the south-east of Irvine, will pass to the east of the town and will terminate near Eglinton Valve Chamber, to the north of Irvine. Between Drybridge and Eglinton it serves approximately 24,200 properties. The diameter of the new PE main is generally 800 mm OD, reducing to 710mm OD after the Long Drive connection and in total is approximately 11 km long.

Description of works:

Design and construction of 5 No auger bored road crossings including detailed design submissions.

Construction of 5No drive and 5No reception pits.

Installation of DN1200 x 24m, 24m, 24m, 27m and 45m steel tube using our TES 48” auger boring machine

Ground Conditions: CLAY, GRAVEL and SAND

Study Project Date  
Unguided Auger Boring at Braden Trunk Main PSC Mains Renew, Irvine, Scotland. M238 07/11/2016
Unguided Auger Boring at Empingham to Hannington Water Pipeline. M130 31/07/2009
Unguided Auger Boring at Hawridge. DB120 28/02/2009