Pipe Bursting

The works comprised pipe bursting existing 225mm sewer and up sizing to accommodate a 355mm SDR 17 MDPE pipe. The section was split into two runs with intermediate manholes removed as they were to be rebuilt and the pipe was welded into two sections, 96m and 208m.

Using a 100 tonne bursting rig the pipe was pulled in with relative ease, despite the presence of a concrete cover on the existing pipe. During the works, it was essential that access was maintained along the private road so the working areas and site accommodation were tightly packed to minimise any disruption to the public. Following installation of the first 96m section, a CCTV inspection of the line was undertaken to check for gradient and flat spots. The pipe passed the inspection without incident. Other works included construction of 6 no new manholes and reconnection to existing system.

Study Project Date  
Pipe Bursting at Ashley Close, Bradford on Avon. DB269 28/09/2012
Pipe Bursting at Windmill Avenue, Kettering. D411 28/09/2012
Pipe Bursting at Laburnum Park, Carnforth. D385 08/05/2012
Pipe Bursting at Beaulieu. DB228 31/01/2012
Pipe Bursting at Cardigan Rural. D354 31/07/2011
Pipe Bursting at YMCA Postley Road, Maidstone. DB190 31/01/2009
C457 - Pipe Bursting at Swayling to Bitterne Water Main Southampton. 31/08/2006

By using this site you are consenting to our use of cookies

Menu