Guided Auger Boring at Paddington New Yard. M219

Client
Crossrail

Project
Remodeling works of the Paddington New Yard.

Description

auger boring

The Crossrail project involves some major remodeling of the Paddington New Yard which is adjacent to Paddington Station, London. The existing Thames Water sewerage network is affected by the new railway and requires diversion along a new route. The Principal Contractor, Costain, approached A. E. Yates Trenchless Solutions Ltd to assess the various different methods to install the pipes to form the new gravity sewer. The most feasible and cost effective option we provided was to use our Bohrtec BM600 guided auger boring machine.

The working areas were very restricted and confined by a new RC retaining wall for the low level Crossrail tracks on one side and the A40 flyover on the other. The drive and reception pits were pre-piled and framed excavations approximately 5m deep. Using our BM600 machine we installed DN600 steel banded concrete jacking pipes over four individual spans totaling 300m. We constructed the permanent manholes, backfilled the excavations and removed the ground support systems.

Ground Conditions were firm dry LONDON CLAY

Study Project Date  
Guided Auger Boring at Paddington New Yard. M219 06/04/2015
Guided Auger Boring DN600 Pentre, Deeside 05/01/2015
Guided Auger Boring at Shreding Green, Iver. M198 18/08/2014
Guided Auger Boring at Minworth Bio Gas, Minworth. M212 09/06/2014
Guided Auger Boring at Colchester Northern Approach Roads, Colchester, Essex. M203 09/12/2013
Guided Auger Boring at Pollard Street, Manchester. M193 03/06/2013
Guided Auger Boring at Portsmouth Flood Alleviation Scheme, Portsmouth. M191 01/04/2013
Guided Auger Boring at Welton Avenue DG5. M187 03/12/2012
Guided Auger Boring at Kinross Pumping Station, Kinross. M184 26/11/2012
Guided Auger Boring at Linstock Rising Main, Carlisle. D373 29/02/2012
Guided Auger Boring at Holt UTX, Trowbridge. M174 30/11/2011
Guided Auger Boring at Secker Wood Sewer Upgrade. MA25 28/02/2011
Guided Auger Boring and Shaft Sinking at Cross Lane, Middlewich. M162 31/07/2010
Guided Augering at West Chiltington. MBA011 30/04/2009
Guided Auger Boring at Wigan 28/02/2009