Culvert Repairs at Millfield Lane, Walbottle, Newcastle upon Tyne. M186

Client
Sir Robert McAlpine

Project
Culvert Repairs

Description

CULVERT REPAIRS

Design and build contract.

  • 1No finished 10.5m diameter x 14m deep caisson shaft
  • Repair and refurbish to an existing 150m long surface water brickwork culvert using fibre reinforced sprayed concrete lining
  • RC inlet and outlet headwalls
  • 12m x DN2100 hand excavated pipe jack

Ground Conditions

Made ground, water table at 8m below ground level

 

Study Project Date  
Culvert Replacement at Lund Terrace FAS, Ulverston UTX, Cumbria. M240 03/04/2017
Grounting of redundant Fuel Pipelines, Fradley Junction, Staffordshire. M223 05/12/2016
Timber Heading at Seaborne Library, Chester University. M230 15/11/2015
Culvert Replacement and Repair at Ferryhill. M228 07/09/2015
NGN Grouting of Vacant Sleeve Annuli. M223 09/03/2015
Culvert Refurbishment at Shaw Brook. M220 02/03/2015
Culvert Repair at Winnings, Newcastle upon Tyne. M211 16/06/2014
Culvert replacement at Ellergill Culvert UTX, Nethertown, Cumbria. M197 02/09/2013
Culvert Replacement at Willowburn, Alnwick. M195 01/07/2013
Culvert works at Jepsons Clough, Horwich, Bolton. M189 04/02/2013
Culvert Repairs at Millfield Lane, Walbottle, Newcastle upon Tyne. M186 02/07/2012
Culvert Replacement at Antley Syke, Accrington. M182 29/06/2012
Culvert Repair at Harwood Brook, Great Harwood - Manholes B2 to B3 relining. M165 30/11/2011
Culvert Refurbishment at HIRPS, Hockery Brook, Hindley. M171 01/04/2011
Culvert Repair at Harwood Brook Culvert Lining and retaining wall, Great Harwood. M165 31/01/2011
Culvert Repair at Riley Lane, Kirkburton, Huddersfield. M152 30/04/2010

By using this site you are consenting to our use of cookies

Menu