September Works Update

M215 Parsons Underbridge Installation of 8 No x 55mm diameter tie bars under the railway using the AEY HDD rig was completed during early August (the tie bars hold back sheet piles driven in cantilever along both sides of the railway embankment). Shaft sinking commenced immediately thereafter on the south side; to date 2 No x 3 metre diameter shafts almost 20 metres deep have been constructed. Equipment is currently being transferred to the north side of the railway embankment to enable the sinking of 2 similar shafts. The 4 shafts form part of the more

Posted by: Yates Group / 28 September 2015 at 10:24 / Comment

AEYTS out spotting Nessy!

AEYTS where contracted in an emergency to supply and install 30 meters of 180mm duct for an electric cable near Inverness. With a long and very picturesque drive we arrived on site in good time, met the client and discussed the way forward. We then went Nessy spotting. Unfortunately due to the hot weather Nessy was not available for a wee chat or appearance. The following morning everything was in place. We drilled through sand and boulders and installed this just after lunch to the clients pleasure. The electric cable was installed that afternoon by more

Posted by: Yates Group / 15 September 2015 at 12:01 / Comment

By using this site you are consenting to our use of cookies