Update on Paddington M219

We have successfully installed 80m of DN600 concrete jacking pipe so far using our BM600 guided auger bore which also includes an additional phase of re-reaming with our hydraulic powered cutter head. We are currently installing pipes on our second drive which is 90m in length. We will then relocate and carry out a further 2No drives of 35m and 80m using the same technique. The work site is located directly underneath the A40 and besides the Hammersmith & Circle Underground line and the Network Rail Heathrow express line. This has an effect on our craneage ...read more

Posted by: Yates Group / 27 May 2015 at 12:47 / Comment