Octobers Update

M198 Shreding Green pipeline diversion Works to divert 2 sections of fuel pipeline under the Grand Union Canal commenced 18 August 2014. The drive pit and reception shaft were constructed during September and two new pipes have been installed under the canal. We are currently installing pipes from the pit / shaft towards the existing live pipelines. The connections will be made when the pipeline is temporarily shut down in mid November. M203 Colchester All foul and surface water shafts have been constructed and the entire surface water pipeline is complete. The ...read more

Posted by: Yates Group / 14 October 2014 at 12:28 / Comment