Update for AEYTS

M198 Shreding Green pipeline diversion Works to divert 2 sections of pipeline under the Grand Union Canal commenced 18 August 2014. M203 Colchester Design for 2 No additional reception shafts and short connecting headings has been finalised and construction work has commenced. All 3 sections of surface water sewer (using the BM600 auger bore) are completed. 3 sections of the surface water sewer (using Soltau 1000 TBM) are complete with the 4th (of 5) currently progressing well. 4 sections of auger bored foul sewer (using the BM400 front steer machine) are complete; the ...read more

Posted by: Yates Group / 01 September 2014 at 11:11 / Comment