July's Update

M203 Colchester 1 remaining (FW drive) shaft for the scheme will be completed at a later date along with 2 additional reception shafts once design has been finalised. 3 sections of surface water sewer (using the BM600 auger bore) have been completed and the equipment has been demobilised. 3 sections of auger bored foul sewer (using the BM400 front steer machine) are complete with the 4th (of 8) currently in progress. 2 sections of the surface water sewer (using Soltau 1000 TBM) are complete with the 3rd (of 5) currently in progress. M204 Whitmore ...read more

Posted by: Yates Group / 09 July 2014 at 13:52 / Comment