M203 Colchester Construction of the drive and reception shafts for the scheme is ongoing. Auger boring of the foul sewers (using the BM400 front steer machine ) and auger boring of the surface water sewers (using the BM600 auger bore ) commenced February. The BM400 is temporarily standing, awaiting replacement auger casings. The BM600 has completed the first drive and will commence the second drive shortly towards trench box 338N located in the open cut works. Due to design changes, 5 sections of the surface water sewer will be constructed using a TBM. The ...read more

Posted by: Yates Group / 16 April 2014 at 11:45 / Comment

AEYTS-Project update

M192 Outwood to Buckland, A25 & A23 All works are complete M202 Corwen All works are complete. M203 Colchester Construction of the drive and reception shafts for the scheme is ongoing. Auger boring of the foul sewers (using the BM400 front steer machine ) and auger boring of the surface water sewers (using the BM600) commenced February although both machines encountered difficulties during the initial drives. Due to design changes, 5 sections of the surface water sewer will be constructed using the Soltau 1000 TBM, this equipment is currently being ...read more

Posted by: Yates Group / 02 April 2014 at 11:18 / Comment

By using this site you are consenting to our use of cookies

Menu