M192 Outwood to Buckland, A25 & A23 All tunnelling works are complete. Extraction of the piles at the Salford and A23 sites is currently in progress. M202 Corwen Construction of the 1500mm ID tunnel using an Iseki TBM is complete. We are currently sealing the shafts and demobilising. M203 Colchester Construction of drive and reception pits for the scheme is ongoing. Auger boring of the foul sewers using the BM400 front steer machine commenced in mid February and auger boring of the 900 surface sewers with the ...read more

Posted by: Yates Group / 05 March 2014 at 10:19 / Comment