Update - Microtunnelling

M192 Outwood to Buckland The Buckland and A25 sites are complete. Extraction of the piles at the Salford and A23 sites will commence following insertion of the carrier pipes (by our client) and backfilling of the shafts. M202 Corwen Construction of the drive and reception shafts is complete. Construction of the 1500mm ID tunnel using an Iseki TBM is ongoing; the tunnel has advanced approximately 75m from the drive shaft towards the A5. M203 Colchester Construction of drive and reception pits for the scheme is ongoing. Auger boring ...read more

Posted by: Yates Group / 10 February 2014 at 11:52 / Comment