AEYTS - Tunnelling Update

M191 Portsmouth We returned to site on the 7 October 2013 and will be undertaking 4 separate auger bore crossings (including one rail and one road crossing) using the AEYTSL BM600 and PB85 equipment during the next 4 months. M192 Outwood to Buckland The 1000mm AS400 Soltau micro-tunnelling machine has completed both of the Bucklands UTX crossings and is currently working at the Salfords UTX twin crossings. The BM600 is currently augering the twin A25 crossings. We propose to commence with sheet piling of the pits for the A23 crossings on 14 ...read more

Posted by: Yates Group / 09 October 2013 at 10:26 / Comment