Works Update for Tunnelling

M191 Portsmouth. Sinking of the 12m shaft at Copnor Road is complete. We are currently completing the base and grouting and expect to demobilise from site 23 August 13. M192 Outwood to Buckland. Site set up commenced 19 August 2013 for the construction of 2 No x twin rail crossing using the 1000mm AS400 Soltau micro-tunnelling equipment. M193 Pollard St, Manchester . The new permanent pipe has been installed between MH4 and MH3. The permanent manhole, a replacement traffic island and re-surfacing in Great Ancotes Street ...read more