Horizontal Directional Drilling Update - Southern Office

DB 286 - Girton College, Cambridge . First of two gravity sewer drills completed. The first installations involved a combination of directional drilling and slip lining , installing 45m of 280mm under the very busy Huntingdon Road into Cambridge . With traffic coming in off the A14, open cut was not an option, given the depth of installation to be 5.5m in the road . Setting the rig up in the grounds off Girton College, the drilling crew followed a predetermined path, drilling the first 36m to a proposed manhole chamber ...read more