Works at Walbottle Site

News from our Microtunnelling Team

At our Walbottle Site we're hoping to get all party approval to commence shaft sinking this week, following the preparatory works which has included surveys, design, void grouting, procurement, over pumping, utility diversions, demolition and strengthening works.

The shaft will be 10.5m internal diameter and will be approximately 14m deep. When complete the shaft will provide suitable access to the existing culvert to allow the lining and strenthening works to be undertaken.

Posted by: Yates Group / 12 September 2012 at 13:53 / Comment