Week 12 of 18 at the White Rose Shopping Centre, Leeds

Contract Update: White Rose Shopping Centre, Leeds


The project comprises of the following:

  • Construction of a new 575 space car park
  • Alterations and widening works to the White Rose Shopping Centre perimeter road
  • Construction of a pre-cast culvert to Cotton Mill Beck with new access roadway above
  • Installation of new perimeter fencing, ANPR controlled access barriers, street lighting, CCTV and a security hut
  • Installation of enhanced lighting to various car parks around the shopping centre
  • Alterations to various existing car park access and egress including pedestrian footways around the shopping centre
  • Construction of a disabled access ramp and bus station alterations on the north side of the shopping centre

We are currently in week 12 of an 18 week programme.

Works are progressing well despite extremely adverse weather conditions, as such we have been delayed approximately 1 week.  We are currently working 7 days a week to pull back the lost time.

We have completed the earthworks and culvert construction and are currently underway with the drainage and retaining walls installation.