Bridge beams in place

Contract Update: Princess Street Bridge, Blackpool


A E Yates are currently in week 10 of a 19 week project on the Princess Street Bridge for Blackpool BC.

The precast concrete bridge beams have been lifted into position this week (w/c 11th January) which is as per the contract programme.  Work now involves completing the in situ concrete deck slab followed by waterproofing, backfill, surfacing and external works in order to re-open the main route into Blackpool town centre before the Easter holidays.