Project carried out for Commercial Estates Group / Bryan G Hall Consultants

This exciting project involved - Large Section 278 Highway Improvement Scheme for a major housing development on the outskirts of Chester.

Highway Improvement Works Included

Amendments to and signalisation (contractor design & UPS) of the very busy Boughton Heath Roundabout at the junction of the A55 & A41. Installation of a SCOOT system, new pedestrian crossing within traffic controlled junction, realignment / widenings, extensive planing & resurfacing, new drainage, signs, lighting and markings. Diversion of SU equipment. Complex traffic management sequences and arrangements to maintain traffic flows with minimum disruption, in liaison with the Highways Authority, Emergency Services, Bus operators and the travelling public.

Works were completed on time and handed over to the Client before Christmas 2011.

Posted by: Yates Group / 16 January 2012 at 13:12 / Comment

Great News

Good News

Comment posted by: Dan / 25 January 2012 at 14:12

By using this site you are consenting to our use of cookies